Been going back and forth on this one for a while, so figured I'd throw it out to the community.
Running a Victron EasySolar-II GX 48/5000 paired with a Fogstar Drift 48V battery bank (two units in parallel) out in the garden office. PV array is 10× 400W panels split across two strings into the onboard MPPT 250/100 — pretty standard stuff for this size of install.
What I'm trying to get my head around is the certification and compliance side once you start adding grid-tied autoconsumption elements. The French original that prompted this was wrestling with their CONSUEL sign-off, which got me thinking about the UK equivalent — DNO notification, G98/G99 compliance, and whether a system like this needs a formal ENA application before you can export or even run parallel with the grid.
My setup is currently island mode only, so I've sidestepped a lot of this. But I'm seriously considering adding grid passthrough for overnight resilience in winter, and that opens a whole compliance rabbit hole.
Specific questions for anyone who's been through it:
- Did your DNO ask for a full G99 application even on a predominantly off-grid system with only incidental grid connection?
- Any issues with the EasySolar-II's built-in grid code settings satisfying UK DNO requirements out of the box?
- Shepherds huts and garden offices — does permitted development change anything on the compliance front, or is it purely electrical regs regardless?
Genuinely curious whether others have navigated this or just stayed fully off-grid to avoid the paperwork entirely.