I've got a bit of a head-scratcher in my garden office build. Running two Victron SmartSolar 100/30s in parallel (one on the south-facing roof array, one on a small east-facing panel for morning gain), both talking to a Cerbo GX via VE.Direct. Total array is about 600W feeding a 200Ah Fogstar Drift lithium bank.
The problem is the Cerbo seems to treat both MPPTs as completely independent, and I'm seeing them occasionally "fight" each other during the absorption phase — one drops out while the other pushes ahead, then they swap. Bulk charge times are longer than they should be on a decent sunny morning. I've got ESS running but I'm starting to wonder if that's actually making things worse rather than better for a standalone off-grid setup with no grid connection.
Has anyone actually dialled this in properly, or is the answer just to ditch ESS config entirely and run both MPPTs in standalone mode with shared battery sense? I've seen conflicting advice on the Victron community forum and honestly some of it reads like it was written for a completely different use case (grid-tied yacht with a Quattro, not exactly my situation).