Two inverters working together?

by Nicola King · 1 week ago 34 views 4 replies
Nicola King
Nicola King
Member
9 posts
Joined Jun 2024
1 week ago
#29039

Been thinking about this a lot lately as I'm planning to expand my setup across both my shepherd's hut and garden office — two separate loads, different priorities, one battery bank.

Currently running a modest Victron MultiPlus-II 3000 with a Fogstar 48V 200Ah lithium bank, and it handles the garden office fine. But I'm wondering whether adding a second inverter for the shepherd's hut (rather than running longer cable runs) is actually viable, or whether I'm opening a can of worms.

Specific questions I can't find clear answers to:

  • Can two inverters share the same battery bank without fighting each other over voltage and charge priority?
  • Does the BMS cope sensibly when two inverters are drawing simultaneously, or does it get confused about load balancing?
  • Is Victron's VE.Bus parallel/stacking the only sensible route here, or are there other options worth considering?

I've read a bit about Victron's MultiPlus units being pairable, but that seems more aimed at doubling capacity on a single circuit rather than serving two physically separate structures.

Has anyone actually done this with an off-grid setup rather than a hybrid grid-tied one? Most of the discussions I find online seem to assume you've got a grid connection as a fallback, which I obviously haven't.

Would love to hear from anyone who's run dual inverters on a single bank — did it cause headaches with the BMS, or does it actually work cleanly? Tempted to post this in the solar section too but figured the battery/BMS angle was the right starting point.

T6 Adventure
T6 Adventure
Member
7 posts
Joined Aug 2024
1 week ago
#29056

Great setup idea @NicolaKing85! A few things worth considering before committing to a configuration:

If your battery bank is centralised, you'll want to think carefully about cable runs to both buildings — voltage drop over distance can really bite you, especially under load. What's the approximate distance between the two structures?

The other question is whether you actually need both inverters running simultaneously or whether the garden office and shepherd's hut have genuinely different usage patterns. If they're rarely both at peak demand together, a single larger inverter with a sub-panel feeding both might honestly be simpler and cheaper.

That said, parallel inverters from the same manufacturer (Victron's MultiPlus range handles this beautifully) can absolutely work well. Just make sure your BMS can communicate load priorities properly.

What inverter brands were you considering? That'll shape the advice considerably.

Defender Dream
Defender Dream
Active Member
18 posts
Joined Oct 2024
1 week ago
#29096

@NicolaKing85 the piece nobody mentions with split-load inverter setups is phase/timing conflicts when both inverters draw surge current simultaneously — your BMS will see a combined inrush that neither inverter would trigger alone, and cheaper BMS units will nuisance-trip or worse, latch off permanently.

If you're running Victron kit, the VE.Bus system handles this elegantly through proper multi-unit communication — two Multiplus units can be configured as a proper parallel or split system with shared DC bus and coordinated switching. Without that communication layer you're essentially hoping the surges don't coincide.

Practically speaking with a motorhome background, I'd treat your shepherd's hut and garden office like separate "consumers" with prioritised loads — critical circuits on one inverter, deferrable loads on the other — and size your BMS disconnect threshold conservatively to accommodate both worst-case draws simultaneously.

What BMS are you currently running?

Squib
Squib
Active Member
10 posts
Joined Aug 2024
1 week ago
#29121

Has anyone actually done this with a single Victron Multiplus feeding both locations via separate circuits, rather than two inverters? Wondering if that sidesteps the phase conflict issue @DefenderDream raised entirely.

In my motorhome I only deal with one inverter obviously, but I'm curious whether the cable run distance between the shepherd's hut and garden office would cause meaningful voltage drop before you even factor in the loads. How far apart are they @NicolaKing85?

Also — what's the BMS situation? If both inverters are pulling simultaneously and you hit a low-voltage cutoff, does the BMS see that as one event or two separate trips? Seems like it could get messy depending on the BMS comms setup.

Tel Scott
Tel Scott
Active Member
11 posts
thumb_up 1 likes
Joined May 2024
1 week ago
#29140

@Squib yeah I ran a single Multiplus II for a while feeding two separate DB boards — works fine until one location pulls a big load and the other browns out. Learned that the hard way when my chest freezer kicked in and killed power to my backup comms gear.

Ended up splitting properly with two inverters off the same Fogstar battery bank. Had to make sure the BMS could handle the combined discharge current from both — easily overlooked that bit.

For @NicolaKing85 — if the hut and office have very different priority levels, worth looking at whether one inverter could be set up with low-battery cutoff before the other, so critical loads always get first dibs on what's left in the bank.