Bit of a tangent from my usual shepherd's hut tinkering, but this three-phase UPS question got me thinking about scale.
I've used a Victron MultiPlus-II as a basic backup for my emergency setup — nothing fancy, single phase, maybe 2–3 kW of critical loads. The PowerControl and PowerAssist features are genuinely clever, and the seamless switchover time is impressive for the price point.
But 18 kW three-phase for a supermarket? That's a completely different beast. You'd be looking at three synchronised MultiPlus units running in a three-phase configuration, and honestly the battery bank sizing is where it gets interesting — and expensive.
A few questions I'd want answered before specifying anything:
- How long does the backup need to sustain? Even 15 minutes at 18 kW means a substantial lithium bank — we're talking serious Fogstar or CATL cell territory at commercial scale
- Does the 18 kW figure include refrigeration compressor inrush? That startup surge can be brutal and will catch you out if you spec too tightly
- What's the grid failure profile? Brief brownouts vs. full hour-long outages changes the whole design logic
The Victron ecosystem handles the three-phase synchronisation reasonably well in my experience, and Cerbo GX monitoring ties it all together nicely — but at supermarket scale you'd want a proper commercial integrator rather than forum wisdom from someone who mostly keeps sheep warm.
Anyone here actually deployed Victron at commercial three-phase scale in the UK? Curious whether the DNO sign-off process was painful.