Been running a Victron SmartSolar 100/30 for about three years now and this caught my attention because I've definitely had moments of uncertainty standing in front of my battery bank wondering which switch goes first.
My setup runs through a Fogstar 12V 200Ah LiFePO4 with its own BMS, and early on I had a couple of occasions where the MPPT threw a fault on startup — nothing catastrophic, just needed a reset. Got me thinking about sequencing.
The general rule I've settled on:
- Battery first — always bring the battery online before anything else
- MPPT connects automatically via the battery voltage
- Solar input follows — the panels then feed into an already-initialised controller
Reverse it on shutdown: solar first (or cover the panels), then disconnect the battery.
The logic being that the controller needs a stable reference voltage from the battery before it sees the PV input. If the solar comes up first into an unpowered MPPT, you can get voltage spikes or the unit hunting around trying to figure out what it's connected to. Some units handle this gracefully, others less so.
That said — does this actually vary between manufacturers? I've only ever run Victron kit so I genuinely don't know if something like a Renogy Wanderer or EPever behaves differently in this regard. Some of those cheaper units don't seem particularly fussed about sequencing from what I've read.
Anyone had actual failures they can attribute to wrong power-up order? Or is this mostly precautionary? Would be good to hear from people running different controllers — especially if you're using a BMS with a pre-charge relay in the mix.